Solar: So Far, So Good

Since July 11, we’ve now been through securing the financing, inspection of the house and roof, setting up the full (detailed) plan, and submitting the permits to the various permit authorities.

Now, we wait. They say that the shortest permit approval will be one week, more typically four weeks, and commonly six weeks or more. That puts us at the end of September.

Probably good timing. It’s really hot outside right now, and I’d hate to have people up there on our roof.

Should go quickly after that.